December, 2009 Herewith I would like to have supported to all thanking to us this year. In particular are valid the thanks Mrs. Schieck, Mr. Richter and Mr. Feddeck for the help from Germany for the project Huahai and with the difficulties linked with it. (Nanjing - Hong Kong - Germany)
July, 2009 By the 7/1/2009 Mr. Georg Schmidt starts with us. Mr. Schmidt brings a long-standing experience in the area of the worldwide commissionings and last was occupied at the company Haver and Böcker. I met Mr. Schmidt in 2008 in Yemen and I was able to convince himself of his abilities.. The commissioning of software and works as a supervisor are no problem for him. He does this by working for years.
Mr. Lenz leaves our company's own request by the 7/15/2009
March, 2009 Mr. Reinhard Lenz Mr. Lenz will be active for the commissionings Worldwide and support our Mr. Rieger and Mr. Garczinski.
From June to December, 2009
End of the commissioning work in Yanbu with final aceptance from the customer
June, 2008
Mr. Thomas Garczinski start in the AISS company.
In 2008
Client Gebr. Pfeiffer AG Kaiserslautern
Up to 1 quarter in 2008 different introductions of mills of the company Gebr. Pfeiffer AG were carried out by Mr. Rieger and me in Turkey, in China, in Iran and in Saudi Arabia. It led to two completely decreases by Mr. Rieger in China and in Iran. My project in Saudi Arabia will be finished in May, 2008. (complete gypsum work with breaker, grinder, calcination, packaging and transport)
In 2007
Client Gebr. Pfeiffer AG By the stable order situation in the house Gebr. Pfeiffer AG I have carried out the whole year together with Mr. Rieger worldwide commissionings for raw mills, coal mills as well as calcining mills for the GPAG. (India, Iran, Lebanon, Turkey, Saudi Arabia, Latvia, Italy and Poland) From September, 2006 to January, 2007
Customer SMS Demag Project Downcoiler
Setting of tasks: Fitting of software of a Downcoilers or parts of it. The adaptation of the software finds in a team of 4 programmations instead of with what the single resources of the project manager A. Schmidt / K. Debus are distributed.
From April, 2006 to September, 2006
Company Lödige
Project Hong Kong AAT new building of the aerial cargo terminal of the company AAT Extent of my order of the company Lödige Construction of a training documentation for the area of Maintenance as well as the service of the plant components All documents were provided with the programme Microsoft Publisher, therefore the customer möglichkeit them has To publish training documents in the in-house Intranet and these new employees to training possibilities to To put possession. Part 2 of my extent was the realisation of the trainings directly in Hong Kong with the operators and the Maintenance crew. Here the arrangements were explained in 4 month Workshop to the staff by AAT and
From December, 2005 to February, 2006
Introduction of a vertical mill with all To and Abförder arrangements in Pole Sroda Slaska for the company Röben Software Siemens tap dance 7 with the visualisation system protool per 6.0 Principal. Gebrüder Pfeiffer AG Kaiserslautern / Arend prozessautomation GmbH & Co. KG
From April to May, 2005
Introduction of a coal mill in Broceni Latvia Principal. Gebrüder Pfeiffer AG Kaiserslautern Support of FIG. Programmer as well as technical Klärungung for the professional bus binding Toshiba Frequenzumrichter to FIG. Control. Construction of Verriegelungsplänen with Autocad.
Principal. Gebrüder Pfeiffer AG Kaiserslautern
From February to April, 2005 Introduction of a vertical mill in Italy Marcelinara Modification of the hydraulic arrangement of the vertical mill as well as the programming of the gear oil care. Principal. Gebrüder Pfeiffer AG Kaiserslautern
IN 2005 January Completion of the cargo arrangement KLM in dam Amster. Client Lödige Systems
From July, 2004 to October, 2004 Enlargement of the cargo arrangement KLM Schiphol Amsterdam airport. Software production and introduction of the arrangement. A new cargo line was built up with 6 decks and a turntable as well as 7 Workstations. System PLC CPU 315 with H1 net as well as professional coach German Post. Client Lödige Systems
November / December, 2004 Introduction of a lime fire extinguishing system in Bulgaria Assenograv Programme Siemens S7, PLC 315 German Post with OP37 (per tool 6.0) Client Arend / Gebr. Pfeiffer AG Kaiserslautern.
From April, 2004 to July, 2004 Modification of the instep hydraulics in a cement mill in Ecuador-Guayaquill, the USA Alabama, Czechia - Detmarovice, China Harbin Jiaoling Xinda, Cheng you, Yantai Client Gebr. Pfeiffer AG Kaiserslautern
From November, 2003 to April, 2004
Commissioning of a cement mill in Yantai/China principal company Arend / Gebr. Pfeiffer AG Kaiserslautern. Programme Siemens S7, PLC 316 German Post with OP37 (per tool 6.0)
From June, 2003 to August, 2003 Software Introduction of a cement mill in Jiaoling (China) principal company Arend / Gebr. Pfeiffer AG Kaiserslautern. Programme Siemens S7, PLC 316 German Post with OP37 (per tool 6.0) From August, 2003 to September, 2003 Enlargement of a Treberanlage in Russia Kazan. Principal company Cousin Kassel. A visualisation (OP17 Was postprepared to form the mistake evaluation komfortabeler)
From March, 2003 to June, 2003 Programming of a chill station with Paternoster and suitable visualisation. Control Siemens 315-2DP visualisation TP270. (with per tool 6.0) Client: Company Dieffenbacher Automation GmbH
From November, 2002 to January, 2003 Introduction of a animal food plant in Russia Kazan. Client Company Vetter Kassel. Siemens PLC 314IFM
From July, 2002 to November, 2002 Commissioning of a gypsum plant in poland / Gacki.
Client Babcock BSH (since 10/02 border brooks BSH). programmer Klaus Krommer. Type PLC Alan Bradley PLC5, customer La Farge
2000 - 2002 Software development and commissioning for steel pressing machines. 15 great steel pressing machines in Hann Münden (the Weser Metal Umformtechnik). As a developing tool Siemens S7 was used 5.1. The controls PLC are from 314IFM to 318DP2 were used. Principal: Fa IET GmbH in Reinhardshagen
1999 - IN 2000 Commissioning of an Oilblending plant (Caltex Tianjin) in China
Client Fa Leitec / Philips. The software was developed on Alan Bradley PLC with professional bus binding to a P8 PLC.
1997 - IN 1999 Software development of the airing and climate technology Dresden AMD by order of the Fa Leitec / Philips with next introduction of the software. As a developing tool the software PDS7 was used, as a control PLC the Philips P8/202
IN 1997 Commissioning of an waste water treatment plant (WWTP) Adana in Turkey Client Siemens Bremen / Erdmann
|
|
 |